Schedule

Call for tenders were sent out in the fall of 2009. In June 2010 heavy machinery began preparing the site for construction. And 16th August 2010 we had the traditionel ground breaking ceremony, attended by the Danish minister of food, agriculture and fisheries.

 

Construction is scheduled to end around newyear 2011/2012. After a series of test runs the plant will start production in April 2012. Delays may occur.

 